The project manager of the retooling project has been replaced by the company in an effort to
Question:
The project manager of the retooling project has been replaced by the company in an effort to finish the project within budget. The replacement project manager wants to determine the rate at which the project is progressing in comparison to the rate planned. What tool or technique can he use to make this determination?
a. Schedule variance
b. Schedule performance index
c. Gantt chart
d. Variance report