You are the project manager on a defense project and are creating a network diagram. Activity A
Question:
You are the project manager on a defense project and are creating a network diagram. Activity A (7 days) and Activity B (12 days) can start immediately. Activity C (3 days) can start after Activity A is complete. Activity D (4 days) and Activity F (3 days) can start after Activity B is complete. Activity E (5 days) can start after Activity C and Activity D are complete. Activity G (6 days) can start after Activity D and Activity F are complete. When Activity E and Activity G are complete, the project is done. What is the critical path?
a. BDE
b. ACE
c. BFG
d. BDG
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: