a) Compare and contrast the project evaluation and review technique (PERT) with the critical path method...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
a) Compare and contrast the project evaluation and review technique (PERT) with the critical path method (CPM). (10 Marks). b) You are the Project Manager of a Company that has just won a bid of $5.4 million to construct a new plant for the Ministry of Trade and Industries. The Ministry needs the plant to go into operation within a year. Therefore, the contract includes the following provisions: • A penalty of $300,000 if your Company has not completed the construction by the deadline 47 weeks from now. • To provide additional incentive for speedy construction, a bonus of $150,000 will be paid to your Company if the plant is completed within 40 weeks. Working with your project team, you have created a list of the various activities below, with the third column providing important additional information for coordinating the scheduling of your team. For any given activity, its immediate predecessors (as given in the third column) are those activities that must be completed by no later than the starting time of the given activity. (Similarly, the given activity is called an immediate successor of each of its immediate predecessors.) Activity A300 B D M N Activity Description Excavate Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting Do the electrical work Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures Install the interior fixtures Immediate Predecessors E, G C FI 1 1 H K, L Estimated Duration 2 weeks 4 weeks 10 weeks 6 weeks 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks 5 weeks 2 weeks 6 weeks Based on the above preamble and table, please answer the following questions: a. Demonstrate using a graphical presentation the flow of the activities such that it could be better visualized (4 Marks). b. Determine the total time required to complete the project if no delays occur? (2 Marks). c. Assess using appropriate examples when the individual activities need to start and finish (at the latest) to meet this project completion time? (2 Marks). d. Determine when the individual activities could start and finish (at the earliest) if no delays occur? (2 Marks). e. Determine the critical bottleneck activities (Critical Path) where any delays must be avoided to prevent delaying project completion? (1 Mark). f. Per the contractual agreement, do you think the project manager and team will pay any penalty? Justify your response. (2 marks). g. Per the contractual agreement, do you think the project manager and team will receive the additional incentive of $150,000 bonus? Justify your response. a) Compare and contrast the project evaluation and review technique (PERT) with the critical path method (CPM). (10 Marks). b) You are the Project Manager of a Company that has just won a bid of $5.4 million to construct a new plant for the Ministry of Trade and Industries. The Ministry needs the plant to go into operation within a year. Therefore, the contract includes the following provisions: • A penalty of $300,000 if your Company has not completed the construction by the deadline 47 weeks from now. • To provide additional incentive for speedy construction, a bonus of $150,000 will be paid to your Company if the plant is completed within 40 weeks. Working with your project team, you have created a list of the various activities below, with the third column providing important additional information for coordinating the scheduling of your team. For any given activity, its immediate predecessors (as given in the third column) are those activities that must be completed by no later than the starting time of the given activity. (Similarly, the given activity is called an immediate successor of each of its immediate predecessors.) Activity A300 B D M N Activity Description Excavate Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting Do the electrical work Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures Install the interior fixtures Immediate Predecessors E, G C FI 1 1 H K, L Estimated Duration 2 weeks 4 weeks 10 weeks 6 weeks 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks 5 weeks 2 weeks 6 weeks Based on the above preamble and table, please answer the following questions: a. Demonstrate using a graphical presentation the flow of the activities such that it could be better visualized (4 Marks). b. Determine the total time required to complete the project if no delays occur? (2 Marks). c. Assess using appropriate examples when the individual activities need to start and finish (at the latest) to meet this project completion time? (2 Marks). d. Determine when the individual activities could start and finish (at the earliest) if no delays occur? (2 Marks). e. Determine the critical bottleneck activities (Critical Path) where any delays must be avoided to prevent delaying project completion? (1 Mark). f. Per the contractual agreement, do you think the project manager and team will pay any penalty? Justify your response. (2 marks). g. Per the contractual agreement, do you think the project manager and team will receive the additional incentive of $150,000 bonus? Justify your response.
Expert Answer:
Related Book For
Fundamentals of Investments Valuation and Management
ISBN: 978-0077283292
5th edition
Authors: Bradford D. Jordan, Thomas W. Miller
Posted Date:
Students also viewed these computer network questions
-
You are the new manager of a local health club. You are being paid what you perceive to be a good monthly salary with an annual three-week paid vacation and good health-care benets. The clubs owner...
-
The operations manager of a company that produces frozen dinners had received numerous complaints from supermarkets about the companys Chick-n-Gravy dinners. The manager spilled/mixed items,...
-
Go to finance.yahoo.com. Compare and contrast the trade (account) receivables turnover and days' sales outstanding of Winn-Dixie Stores Inc., Dean Foods Co., and Lifeway Foods Inc. Read the business...
-
Mixing together solutions of acetic acid and sodium hydroxide can make a buffered solution. Explain. How does the amount of each solution added change the effectiveness of the buffer?
-
a. Suppose that you want to borrow a widget beginning in December of Year 0 and ending in March of Year 1. What payment will be required to make the transaction fair to both parties? b. Suppose that...
-
For the following firms, find the return on equity using the three components of the DuPont identity: operating efficiency, as measured by the profit margin (net income/sales); asset management...
-
What is the internal rate of return of the following cash flow diagram? a. 20 percent b. 18.2 percent c. 17.5 percent d. 15 percent $30 $31 0 1 2 3 $30 $15
-
Yard Tools manufactures lawnmowers, weed-trimmers, and chainsaws. Its sales mix and contribution margin per unit are as follows. Yard Tools has fixed costs of $4,200,000. Instructions Compute the...
-
5.) A hoop of 6 kg and radius .15 m is rolling down a 40-degree incline with 5 m length, what acceleration does it travel down the incline? How long does it take to get down the incline?
-
A highly viscous liquid discharges from a large container through a small-diameter tube in laminar flow. Disregarding entrance effects and velocity heads, obtain a relation for the variation of fluid...
-
Given the function f(x) = x- 2, find the value of f (-2) in simplest form.
-
Do you think that using flextime, telecommuting, job sharing, or compressed workweeks is really going to motivate employees? Why or why not?
-
Harris Corporation has $243 million in cash and 147 million shares outstanding. Suppose the corporate tax rate is 35% and investors pay no taxes on dividends, capital gains, or interest income....
-
As the head of HR, would you rather change narrow pay levels into broadbands? Can you think of any disadvantages to doing so?
-
Based on what is in the chapter, should the ACA federal health care legislation remain in its current form, or should we rescind the requirement that employers and/or employees have to pay a fine if...
-
If you were in charge, would you put an EAP into place at your company? How about an EWP? Why or why not?
-
In the lungs, oxygen diffuses from the gas phase to blood across the alveolar membrane. Since the thickness of this membrane is very small (0.20 microns), it behaves like a thin aqueous layer for O...
-
Explain the regulation of the secretions of the small intestine.
-
A key concern in technical analysis such as the Dow theory is to identify turning points in market direction and thereby time the market. What are the implications of market efficiency for market...
-
Which is larger, gross margin or operating margin? Can either be negative? Can both?
-
Suppose the following three defense stocks are to be combined into a stock index in January 2007 (perhaps a portfolio manager believes these stocks are an appropriate benchmark for his or her...
-
In a steam power plant, coal is burned at the rate of 50 lbm/min. The percentage of ash in the coal is 9% by mass. The combustion of coal takes place in a fluidized bed reactor and the ash in the...
-
2-Mercaptoethanol (C 2 H 6 OS) is produced by reacting ethylene oxide (C 2 H 4 O) with hydrogen sulfide (H 2 S) as per the following reaction equation. The reaction takes place in the presence of...
-
Chlorobenzene is produced by direct chlorination of benzene. However, a parallel reaction that produces dichlorobenzene hexachloride also occurs. The parallel reactions are shown here. The single...
Study smarter with the SolutionInn App