End item X is composed of 3 subassemblies: A, B, C. A is assembled using 4 Ds
Question:
End item X is composed of 3 subassemblies: A, B, C. A is assembled using 4 Ds and 3 Es. B is made of 3 Fs and 2 Gs; and C is made of 3 Hs. On- hand inventories are 30 Bs, 40 Ds, 20 Gs, and 300 Es. Scheduled receipts are 10 As at the start of wk 4, 30 As at the start of wk 6, and 100 Cs at the start of wk 3. One hundred Xs will be shipped at the start of week 7 and another 150 at the start of wk 8. Lead times are 2 wks for subassemblies and 1 wk for components D, E, F, G, and H. Final assembly of X requires one wk. Include an extra 11 % scrap allowance in each planned order of D and 10 % in each planned order of G. The minimum order size for E is 150 units.
Develop each of the following:
A. A product structure tree
B. A master schedule for X
A material requirements plan for A, B, C, D, E, F, G, and H