PowerWorld Simulator case Problem 11_27 duplicates the system from Problem 11.24, except the generators are modeled using
Question:
PowerWorld Simulator case Problem 11_27 duplicates the system from Problem 11.24, except the generators are modeled using a two-axis model, with the same \(X_{d}^{\prime}\)
and \(\mathrm{H}\) parameters are in Problem 11.24. Compare the critical clearing time between this case and the problem 11.24 case.
Data From Problem 11.24:-
Open PowerWorld Simulator case, which models the Example 6.9 with transient stability data added for the generators. Determine the critical clearing time (to the nearest 0.01 second) for a fault on the line between buses 2 and 5 at the bus 5 end which is cleared by opening the line.
Data From Example 6.9:-
Data From Table 6.1 and 6.2 and 6.3:-
Step by Step Answer:
Power System Analysis And Design
ISBN: 9781111425777
5th Edition
Authors: J Duncan Glover, Mulukutla S Sarma, Thomas Overbye