The customer has requested a five-week delay on the project while they rebuild a warehouse used for

Question:

The customer has requested a five-week delay on the project while they rebuild a warehouse used for manufacturing a key piece of the project. This delay wasn’t planned, but the project couldn’t continue without it. The company is limited on available resources. This delay will be best shown in what?

a. Network diagram

b. Responsibility assignment matrix

c. Work breakdown structure (WBS)

d. Budget