The project to roll out tablets for use in a 500-bed hospital is going well, except for

Question:

The project to roll out tablets for use in a 500-bed hospital is going well, except for a minor problem in the MRI area, where the wireless access isn’t working as expected. What documentation should be used to track and manage this problem?

a. Stakeholder register

b. Stakeholder management plan

c. Issue log

d. Charter