PERT network has these time estimates: optimistic = 1.6,most likely =5.4,and pessimistic = 10. What is its
Fantastic news! We've Found the answer you've been seeking!
Question:
PERT network has these time estimates: optimistic =
1.6,most likely =5.4,and pessimistic = 10. What is its expected activity time and
variance?
(Do not round intermediate calculations. Round final answer to two decimal places.)
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Posted Date: