Question: please Jennifer is working on a project plan in Microsoft Project, and she wants to specify that a task is progressing according to its planned

please

Jennifer is working on a project plan in Microsoft Project, and she wants to specify that a task is progressing according to its planned schedule. Which step should she take to accomplish the task? A O In the Gantt view or other task view, select the task and on the Task tab, in the Schedule group, click Mark the Track. B O In the Gantt view or other task view, select the task and on the Task tab, in the Schedule group, click Mark Track. C O In the Gantt view or other task view, select the task and on the Task tab, in the Schedule group, click Mark on Track