Question: The following table represents a plan for a project: JOB NO. 1 2 3 4 5 6 7 8 9 10 11 PREDECESSOR JOB

    

The following table represents a plan for a project: JOB NO. 1 2 3 4 5 6 7 8 9 10 11 PREDECESSOR JOB (S) - 1 1 1 2 3 4 5, 6 8 7 9, 10 TIMES (DAYS) a 2 Expected completion time 31 4 3 1 1 1 2 2 3 5 b. Indicate the critical path. m b 3 2 5 4 3 2 R 4 4 4 7 4 3 12 11 5 3 9 6 12 5 8 c. What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.) days