Question

1 Approved Answer

Under This is the work table calculated production in a unit week. ACTIVITY PREVIOUS ACTIVITIES PESIMISTIC TIME NORMAL TIME OPTIMISTIC TIME K L A

 

Under This is the work table calculated production in a unit week. ACTIVITY PREVIOUS ACTIVITIES PESIMISTIC TIME NORMAL TIME OPTIMISTIC TIME K L A B CD CD CD E F,G|H|H|I,K 24 10 8 12 13 8 14 12 16 16 12 18 16 A B C D E F G H I J 23 4 6 6 49 10 628 12 18 12 11 14 14 20 19 16 17 S355 Calculate the Probability of Completion of the Project completed in 61 weeks and the Probability of Completion of the Project in 62 weeks, How do you respond to the two outcomes?

Step by Step Solution

3.34 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

To calculate the probability of completing the project in a certain number of weeks you can use the PERT Program Evaluation and Review Technique analy... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these General Management questions