Any approved budget increase should be: a. Added to the project contingency fund and only used as

Question:

Any approved budget increase should be:

a. Added to the project contingency fund and only used as a last resort

b. Added to the project’s cost baseline

c. Added to the project’s lessons learned

d. Offset by budget take-aways from direct cost accounts