Question: A CNC machining center has a programmed cycle time = 25.0 min for a certain part. The time to unload the finished part and load

A CNC machining center has a programmed cycle time = 25.0 min for a certain part. The time to unload the finished part and load a starting work unit = 5.0 min.
(a) If loading and unloading are done directly onto the machine tool table and no automatic storage capacity exists at the machine, what are the cycle time and hourly production rate?
(b) If the machine tool has an automatic pallet changer so that unloading and loading can be accomplished while the machine is cutting another part, and the repositioning time = 30 sec, what are the total cycle time and hourly production rate?
(c) If the machine tool has an automatic pallet changer that interfaces with a parts storage unit whose capacity is 12 parts, and the repositioning time = 30 sec, what are the total cycle time and hourly production rate? Also, how long does it take to perform the loading and unloading of the 12 parts by the human worker, and what is the time the machine can operate unattended between parts changes?

Step by Step Solution

3.61 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a T c 250 50 300 minpc R c 6030 20 pchr b T c ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

795-C-S-A-I (649).docx

120 KBs Word File

Students Have Also Explored These Related Artificial Intelligence Questions!