A company needs to manage a project which consists of the following set of activities. a. Draw

Question:

A company needs to manage a project which consists of the following set of activities.
Days Predecessor Activity Required Activities A 5 A 4 A B. C D 5 E D, F G 4 3.

a. Draw an AON network.
b. Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest Finish time (LF), and Slack for all the activities.
c. What is the critical path for the project and how long should it take to complete it? identify each path through the network using activity name (example: A, B etc.) from beginning to end, and its expected length of time.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managing Supply Chain and Operations An Integrative Approach

ISBN: 978-0132832403

1st edition

Authors: Thomas Foster, Scott E. Sampson, Cynthia Wallin, Scott W Webb

Question Posted: