Question: A construction contractor is responsible for a project with seven key tasks. Some of the tasks can begin at any time, but others have predecessor

A construction contractor is responsible for a project with seven key tasks. Some of the tasks can begin at any time, but others have predecessor tasks that must be completed previously. The individual tasks can be carried out at standard times or they can be expedited ("crashed"). The cost of executing the task increases by a certain cost per day if its time is shortened. The following table shows the information describing the tasks of the project, their standard and minimum times (in days), their standard costs, the crashing cost per day shortened, and the predecessor(s):
Cost/ Task Minimum Standard Standard Day to Predecessor Cost Tasks Number Time Time Shorten 1,600 6 12 100 None 2 16 2,4

The project has a deadline of 40 days, which the contractor is committed to meet.
a. If no crashing is done, how long will the project take and what will be its cost?
b. Which activities should be crashed to achieve the least-cost schedule that meets a 40-day deadline? What is the difference between its cost and the cost in part (a)?

Cost/ Task Minimum Standard Standard Day to Predecessor Cost Tasks Number Time Time Shorten 1,600 6 12 100 None 2 16 2,400 75 None 3 16 24 2,900 120 4 14 20 1,900 100 1,2 14 16 3,800 140 3 12 16 2,900 165 3 12 60 1,300 2.

Step by Step Solution

3.50 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a There are no crashing days Every task has some minimum time to complete it The minimum time standard time and cost of every task is given in Table 1 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1301-M-N-A-O(977).docx

120 KBs Word File

Students Have Also Explored These Related Numerical Analysis Questions!