Question: A construction contractor is responsible for a project with seven key tasks. Some of the tasks can begin at any time, but others have predecessor
.png)
The project has a deadline of 40 days, which the contractor is committed to meet.
a. If no crashing is done, how long will the project take and what will be its cost?
b. Which activities should be crashed to achieve the least-cost schedule that meets a 40-day deadline? What is the difference between its cost and the cost in part (a)?
Cost/ Task Minimum Standard Standard Day to Predecessor Cost Tasks Number Time Time Shorten 1,600 6 12 100 None 2 16 2,400 75 None 3 16 24 2,900 120 4 14 20 1,900 100 1,2 14 16 3,800 140 3 12 16 2,900 165 3 12 60 1,300 2.
Step by Step Solution
3.50 Rating (170 Votes )
There are 3 Steps involved in it
a There are no crashing days Every task has some minimum time to complete it The minimum time standard time and cost of every task is given in Table 1 ... View full answer