A contractor agreed to build a skating rink for the plaintiff at a price of $180,000. The

Question:

A contractor agreed to build a skating rink for the plaintiff at a price of $180,000. The rink was to be completed by December 1 and was designed to replace a similar but older rink that the plaintiff rented for $800 a month. A clause in the contract awarded the plaintiff “$100 per day in liquidated damages” for each day after December 1 that the rink was not completed. Was this a valid liquidated damages clause? Explain.


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

The Legal Environment of Business A Critical Thinking Approach

ISBN: 978-0132664844

6th Edition

Authors: Nancy K Kubasek, Bartley A Brennan, M Neil Browne

Question Posted: