Question: A contractor agreed to build a skating rink for the plaintiff at a price of $180,000. The rink was to be completed by December 1
A contractor agreed to build a skating rink for the plaintiff at a price of $180,000. The rink was to be completed by December 1 and was designed to replace a similar but older rink that the plaintiff rented for $800 a month. A clause in the contract awarded the plaintiff “$100 per day in liquidated damages” for each day after December 1 that the rink was not completed. Was this a valid liquidated damages clause? Explain.
Step by Step Solution
★★★★★
3.30 Rating (176 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Yes it is a valid liquidated damages clause The liquid... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
Document Format (1 attachment)
244-L-B-L-L-E (1926).docx
120 KBs Word File
