Question: A contractor departed from the specifications at a number of points in a contract to build a house. The cost to put the house in
A contractor departed from the specifications at a number of points in a contract to build a house. The cost to put the house in the condition called for by the contract was approximately $14,000. The contractor was sued for $50,000 for breach of contract and emotional disturbance caused by the breach. Decide.
Step by Step Solution
3.36 Rating (159 Votes )
There are 3 Steps involved in it
The owner could recover 14000 on the basis that much money wou... View full answer