Question: A custom-made product is produced by processing materially sequentially through four departments. To process material, department #1 requires .5 hours per unit, department #2 requires

A custom-made product is produced by processing materially sequentially through four departments. To process material, department #1 requires .5 hours per unit, department #2 requires .6 hours per unit, department #3 requires .2 hours per unit, and department #4 requires .5 hours per unit.
If the original order is processed in three batches of 100 units each, how many hours will pass before the first unit of each of the first two batches is completed and ready for shipment? (Hint: splitting and overlapping of these three batches is taking place; determine the completion time for the first piece of the first batch of 100 units, then the completion time of the first piece of the second batch of 100 units).
A. 50.0 hours, and 180.0 hours
B. 150.5 hours, and 210.5 hours
C. 130.5 hours, and 190.5 hours
D. 110.0 hours, and 170.5 hours
E. none of the above

Step by Step Solution

3.38 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

C 1305 hours and 1905 hours First batch Department 1 100 X 0550 hours Depart... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-A-C-P-A(3120).docx

120 KBs Word File

Students Have Also Explored These Related Cost Accounting Questions!