Question: A foundation engineer estimates that the settlement of a proposed structure will not exceed 2 in. with 95% probability. From a record of performance of
A foundation engineer estimates that the settlement of a proposed structure will not exceed 2 in. with 95% probability. From a record of performance of many similar structures built on similar soil conditions, he finds that the coefficient of variation of the settlement is about 20%. If a normal distribution is assumed for the settlement of the proposed structure, what is the probability that the proposed structure will settle more than 2.5 in
Step by Step Solution
3.31 Rating (154 Votes )
There are 3 Steps involved in it
Calculate the coefficient of variation Here the stan... View full answer