Question: A manufacturing project has five independent phases whose completion must be sequential. The time to complete each phase is a random variable. The mean and

A manufacturing project has five independent phases whose completion must be sequential. The time to complete each phase is a random variable. The mean and standard deviation of the time for each phase are shown below.
(a) Find the expected completion time.
(b) Make a 2-sigma interval around the mean completion time (μ ± 2σ).
A manufacturing project has five independent phases whose completion must

Phase Mean (hours) Std. Dev. (hours) Set up dies and other tools Milling and machining Finishing and painting Packing and crating Shipping 20 10 14 4 48 6

Step by Step Solution

3.34 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Using Rule 3 total time 201014648 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

485-M-S-D-P-D (775).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!