Question: A manufacturing project has five independent phases whose completion must be sequential. The time to complete each phase is a random variable. The mean and
(a) Find the expected completion time.
(b) Make a 2-sigma interval around the mean completion time (μ ± 2σ).
.png)
Phase Mean (hours) Std. Dev. (hours) Set up dies and other tools Milling and machining Finishing and painting Packing and crating Shipping 20 10 14 4 48 6
Step by Step Solution
3.34 Rating (169 Votes )
There are 3 Steps involved in it
a Using Rule 3 total time 201014648 ... View full answer