Question:

A new alloy can be produced by Process A, which costs $200,000 to implement. The operating cost will be $15,000 per quarter with a salvage value of $25,000 after its 2-year life.

Process B will have a first cost of $250,000, an operating cost of $10,000 per quarter, and a $40,000 salvage value after its 4 year life. The interest rate is 8% per year compounded quarterly. Using present value analysis which process should be selected?