Question: A new order filling system needs to be installed as soon as possible. The table on the next page lists the projects activities and their
Set up and solve an LP model using Excel to crash this project to 24 days. What is the total crashing cost?
.png)
IMMEDIATE STANDARD ACnvii PREDECESSORS TIME (DAYS) STANDARD CRASH TIME CRASH COST COST (DAYS) S 3,00 $4,700 S 3,700 S 2,600 $ 4,000 2,800 $10,900 $ 3,800 $3,000 $3,400 $1,600 $1,900 D, E B, C F, G $2,600