A project is shown in the following dependence table.

(a) What is the probability that the project will be completed before week 17?

(b) By what time is there a probability of 0.95 that the project will befinished?

A project is shown in the following dependence table. (a)

Activity Depends on Duration (weeks) Optimistic Most lkely Pessimistic 4 10 4 K H 4 C, G, K1

Step by Step Solution

3.58 Rating (176 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The following printout shows an analysis of the timing of the project From this you can see that the probability the project is finished before 17 is ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

180-M-S-Q-M (421).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!