Question: Abandonment and Expansion in the previous problem, suppose the scale of the project can be doubled in one year in the sense that twice as
Abandonment and Expansion in the previous problem, suppose the scale of the project can be doubled in one year in the sense that twice as many units can he produced and sold. Naturally, expansion would be desirable only if the project is a success. This implies that if the project is a success, projected sales after expansion will be 18,000. Again assuming that success and failure are equally likely, what is the NPV of the project? Note that abandonment is still an option if the project is a failure. What is the value of the option to expand?
Step by Step Solution
3.52 Rating (159 Votes )
There are 3 Steps involved in it
If the project is a success present value of the future cash flows will be PV future CFs 6518000PVIF... View full answer