Alma Company manufactures sleeping bags. A heavy-duty zipper is one part the company orders from an outside supplier. Information pertaining to the zipper is as follows:

Economic order quantity ...4,200 units

Average daily usage .......200 units

Maximum daily usage .......240 units

Lead time ............3 days

Required:

1. What is the reorder point assuming no safety stock is carried?

2. What is the reorder point assuming that safety stock is carried?