Question: Alpha Great Construction was the best selection to build the Stoddard Temple for the amount of $2,500,000. The project broke ground in 2010 and was

Alpha Great Construction was the best selection to build the Stoddard Temple for the amount of $2,500,000. The project broke ground in 2010 and was then completed in 2011. Below the cost and other data are shown below:


Alpha Great Construction was the best selection to build the


Alpha Great Construction is using the percentage of completion method to recognize revenue:
Compute the amount of gross profit recognized in 2010 and2011

Year Cost incurred during the year Estimated cost to complete Biling during the year Cash collections during the year 2010 S 555000 1200000 S 1500000 S 450000 1500000 S 2011 350000 1400000

Step by Step Solution

3.55 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Year 2010 2011 Contract value Cost incurred during the year ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

68-B-A-G-F-A (1569).xlsx

300 KBs Excel File

Students Have Also Explored These Related Accounting Questions!