Question: Amy Van Dyken Construction Company uses the percentage-of-completion method of accounting. In 2008, Van Dyken began work under contract #E2-D2, which provided for a contract

Amy Van Dyken Construction Company uses the percentage-of-completion method of accounting. In 2008, Van Dyken began work under contract #E2-D2, which provided for a contract price of $2,200,000. Other details follow:


Amy Van Dyken Construction Company uses the percentage-of-comple


Instructions
(a) What portion of the total contract price would be recognized as revenue in 2008? In 2009?
(b) Assuming the same facts as those above except that Van Dyken uses the completed-contract method of accounting, what portion of the total contract price would be recognized as revenue in2009?

2008 2009 Costs incurred to date Estimated costs to compiete, as of December 31 Billings during the year S 480,000 1,120,000 420,000 $1,425,000 1,680,000

Step by Step Solution

3.30 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a 2008 x X 2200000 660000 2009 x 2200000 con... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

117-B-A-R-R (336).docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!