Question: An engineer is creating a project scheduling program and recognizes that the tasks making up the project are not always completed on time. However, the

An engineer is creating a project scheduling program and recognizes that the tasks making up the project are not always completed on time. However, the completion proportion tends to be fairly high. To reflect this condition, he uses the pdf

fY(y; θ) = θ yθ−1, 0 ≤ y ≤ 1, and 0 < θ

where y is the proportion of the task completed. Suppose that in his previous project, the proportions of tasks completed were 0.77, 0.82, 0.92, 0.94, and 0.98. Estimate θ.

Step by Step Solution

3.38 Rating (182 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

In Implies Or e ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

681-M-C-M-S (798).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!