Question: Assume that the project in Problem 3 has the following activity times (in months): a. Find the critical path. b. The project must be completed
Assume that the project in Problem 3 has the following activity times (in months):
a. Find the critical path.
b. The project must be completed in 11/2 years. Do you anticipate difficulty in meeting the deadline?Explain.
Activity | A B C D E F G Time 4 6 2 6 3 3 5
Step by Step Solution
3.42 Rating (161 Votes )
There are 3 Steps involved in it
a Critical Path ADG b The critical path activities ... View full answer