Question: Atman Enterprises assembles satellites using customer supplied parts and materials. A customer has asked Atman to bid on a new model of satellites and estimates
Required:
a. Determine the total number of hours required to assemble all eight satellites, assuming no learning takes place. What is the associated labor cost?
b. Repeat requirement (a) assuming that Atman expects to realize a 90% learning curve for such jobs.
c. Comparing your answers for parts (a) and (b), what conclusions do you draw about the importance of including the effects of learning when bidding for jobs?
Step by Step Solution
3.43 Rating (172 Votes )
There are 3 Steps involved in it
a Atman expects to spend 8 20000 hours 160000 hours to assemble 8 satellites Its expected cost is ... View full answer