Question: Bailey Builders Corporation accepted a three- year, $ 1,000,000 fixed- fee contract to renovate a parking deck. Bailey uses the percentage- of- completion method and
.png)
Prepare the journal entries required in each year to record the contract. Show all supporting computations.
Contract price $1,000,000 2015 2016 2017 Actual construction costs incurred during the year 350,000 S525,000 S 50,000 Construction costs incurred in prior years Cumulative construction costs incurred to date Estimated costs to complete Estimated total costs 875,000 $350,000 S875,000 925,000 350,000 450,000 25,000 Progress billings made during the year Cash collections during the year $800,000 900,000 $925,000 $500,000 S300,000 $200,000 400,000 S350,000 $250,000
Step by Step Solution
3.45 Rating (181 Votes )
There are 3 Steps involved in it
2015 2016 2017 Actual cumulative costs incurred to date 350000 875000 925000 Estimated total costs 8... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
578-B-A-V-I (1584).docx
120 KBs Word File