Basic Data Review for Construction Project Equipment Arrangement Use the data in the table above and answer

Question:

Basic Data Review for Construction Project Equipment Arrangement
Cycle Time (hours) Description Potential Difference Step Actual Read basic data package 4 4 Write, type, proof, sign, co

Use the data in the table above and answer the following questions in the space provided below:
What are the sources of value-added and non-value-added work in this process?
Where are the main opportunities to improve the cycle time of this process, with respect to both actual time used and the potential best times? What strategy would you use?
Step 10: Resolve Open Issues required 104 hours (potential) versus 106 hours (actual). Is there an OFI here? Why or why not? If so, how would you attack it?
What do you think are the most difficult critical issues to deal with when designing a sound cycle time study such as this one?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Advanced Accounting

ISBN: 978-1118037911

1st Canadian Edition

Authors: Gail Fayerman

Question Posted: