Question: Bradley's materials quantity variance for the current month was exactly one-half of its materials price variance. Both variances were unfavorable. The company's cost accountant has
Bradley's materials quantity variance for the current month was exactly one-half of its materials price variance. Both variances were unfavorable. The company's cost accountant has supplied the following standard cost information.
Standard price per pound of materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $15
Actual pounds purchased and used during the month . . . . . . . . . . . . . . . . . . . . 600 pounds
Actual cost per pound of materials purchased and used . . . . . . . . . . . . . . . . . . . . . . . . $18
Actual units manufactured during the month . . . . . . . . . . . . . . . . . . . . . . . . . . . . 450 units
Normal productive output per month . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 480 units
Instructions
a. Compute Bradley's materials price variance.
b. Compute the standard quantity of materials allowed for producing 450 units of product.
c. Record the journal entry to charge Work in Process for the cost of materials used during the month.
d. Assume Bradley's overhead volume variance is four times the amount of its materials quantity variance. Is the volume variance favorable or unfavorable? How do you know?
Step by Step Solution
3.22 Rating (157 Votes )
There are 3 Steps involved in it
Bradley a MPV Actual Quantity Standard Price Actual Price 600 pounds 15lb 18lb 1800 or 1800 Unfavora... View full answer