Question: Candycane Co. is trying to determine how long it takes for one of its products to pass through the production process. The following information was
Candycane Co. is trying to determine how long it takes for one of its products to pass through the production process. The following information was assembled regarding how many days the product spends in various production activities:
.png)
(a) Which of the above activities are value-added activities?
(b) What is Candycane's total cycle time?
(c) Determine Candycane's manufacturing efficiency ratio.
Number of days Activity Inspection Storage Assembly Handling Painting Packaging 12 14
Step by Step Solution
3.41 Rating (157 Votes )
There are 3 Steps involved in it
a Value Added Activities are Assembly Painting Packagi... View full answer