Question: Colby Company has a process costing system in which the weighted-average method is used. The company adds all materials at the beginning of the process
.png)
What was the materials cost of the work in process inventory at March 31?
A. $11,220
B. $7,500
C. $5,100
D.$7,650
Units 22,000 90,000 Materials cost Work in process at March 1 Units started during March S11.000 $46,000 Units completed and transferred to next department During March 97, 000
Step by Step Solution
3.53 Rating (163 Votes )
There are 3 Steps involved in it
D 7650 Calculation of materials cost of the work in process inventory at M... View full answer