Question: Compute activity-based cost rate, time equations CAN Company sells multiple products and uses a time-driven ABC system. The companys products must be wrapped individually before
Required
(a) Using the principles discussed in this chapter and time-driven ABC, what is the rate per hour for each packaging and shipping employee at CAN?
(b) On average, it takes one packaging and shipping employee 15 minutes to prepare a package and label, independent of the number or types of items in the shipment, plus 6 minutes per item to bubble wrap and pack it in the carton. Using CAN’s time-driven ABC system, what is the packaging and shipping cost assigned to Order 705, which consisted of 40 items?
Step by Step Solution
3.42 Rating (168 Votes )
There are 3 Steps involved in it
a The practical capacity per month for each packaging and shipping employee is 8 125 ho... View full answer