Question: Compute the multifactor productivity measure for an 8 hour day in which the usable output was 503 units, produced by 5 workers who used 705

Compute the multifactor productivity measure for an 8 hour day in which the usable output was 503 units, produced by 5 workers who used 705 pounds of materials. Workers have an hourly wage of 19 and material cost is 1.9 per pound. Overhead is 1.3 times labor cost.
The multifactor productivity (units/$) = (round to 4 decimal places)

Step by Step Solution

3.33 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The productivity is calculated by following formula Productiv... View full answer