Question: Compute the total job cost for each of the following scenarios: a. If the direct labor cost method is used in applying factory overhead and
a. If the direct labor cost method is used in applying factory overhead and the predetermined rate is 100%, what amount should be charged to Job 2010 for factory overhead? Assume that direct materials used totaled $5,000 and that the direct labor cost totaled $3,200.
b. If the direct labor hour method is used in applying factory overhead and the predetermined rate is $10 an hour, what amount should be charged to Job 2010 for factory overhead? Assume that the direct materials used totaled $5,000, the direct labor cost totaled $3,200, and the number of direct labor hours totaled 250.
c. If the machine hour method is used in applying factory overhead and the predetermined rate is $12.50 an hour, what amount should be charged to Job 2010 for factory overhead? Assume that the direct materials used totaled $5,000, the direct labor cost totaled $3,200, the direct labor hours were 250 hours, and the machine hours were 295 hours.
Step by Step Solution
3.32 Rating (187 Votes )
There are 3 Steps involved in it
a Direct labor cost method3200 direct labor cost x 100 3200 ... View full answer
Get step-by-step solutions from verified subject matter experts