Question: Consider the following time series data: Using the nave method (most recent value) as the forecast for the next week, compute the following measures of
.png)
Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy:
a. Mean absolute error
b. Mean squared error
c. Mean absolute percentage error
d. What is the forecast for week 7?
Week 23 4 5 6 Valu18 13 6 1 7 14