Craig, Inc., has provided the following information for one of its products for each hour of production:

Question:

Craig, Inc., has provided the following information for one of its products for each hour of
production:
Actual velocity: 100 units (per hour)
Move time: 20 minutes
Inspection time: 18 minutes
Rework time: 12 minutes
Required:
1. Calculate MCE. Comment on its significance.
2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times.
3. What if waste is reduced by 40 percent? What is the new MCE? New cycle time?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cornerstones of Cost Management

ISBN: 978-1285751788

3rd edition

Authors: Don R. Hansen, Maryanne M. Mowen

Question Posted: