Question: Cycle time efficiency and JIT Walker Brothers Company is considering the installation of a JIT manufacturing system in the hope that it will improve the
Cycle time efficiency and JIT Walker Brothers Company is considering the installation of a JIT manufacturing system in the hope that it will improve the company??s overall processing cycle efficiency. Data from the traditional system and estimates for the JIT system are presented here for their Nosun product:

Required (a) Calculate processing cycle efficiency (PCE) under the traditional and JIT systems for the Nosun product. (b) Based strictly on your PCE calculations above, should Walker Brothers implement the JIT system? Explain.
TRADITIONAL SYSTEM 4 hours 40 minutes 80 minutes 2 hours TIME CATEGORY JIT SYSTEM 1 hour Storage Inspection Moving Processing 5 minutes 20 minutes 75 minutes
Step by Step Solution
3.35 Rating (164 Votes )
There are 3 Steps involved in it
a PCE in minutes under the traditional system equals 120120 80 24... View full answer