Question: Cycle time efficiency and JIT Walker Brothers Company is considering the installation of a JIT manufacturing system in the hope that it will improve the

Cycle time efficiency and JIT Walker Brothers Company is considering the installation of a JIT manufacturing system in the hope that it will improve the company??s overall processing cycle efficiency. Data from the traditional system and estimates for the JIT system are presented here for their Nosun product:

TRADITIONAL SYSTEM 4 hours 40 minutes 80 minutes 2 hours TIME CATEGORY

Required (a) Calculate processing cycle efficiency (PCE) under the traditional and JIT systems for the Nosun product. (b) Based strictly on your PCE calculations above, should Walker Brothers implement the JIT system? Explain.

TRADITIONAL SYSTEM 4 hours 40 minutes 80 minutes 2 hours TIME CATEGORY JIT SYSTEM 1 hour Storage Inspection Moving Processing 5 minutes 20 minutes 75 minutes

Step by Step Solution

3.35 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a PCE in minutes under the traditional system equals 120120 80 24... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

62-B-M-A-D-B-S (247).docx

120 KBs Word File

Students Have Also Explored These Related Managerial Accounting Questions!