Question: Dalton Construction Co. contracted to build a bridge for $5,000,000. Construction began in 2010 and was completed in 2011. Dalton uses the percentage-of-completion method. Instructions
Dalton Construction Co. contracted to build a bridge for $5,000,000. Construction began in 2010 and was completed in 2011.
.png)
Dalton uses the percentage-of-completion method.
Instructions
(a) How much revenue should be reported for 2010? Show your computation.
(b) Make the entry to record progress billings of $1,650,000 during 2010.
(c) Make the entry to record the revenue and gross profit for 2010.
(d) How much gross profit should be reported for 2011? Show yourcomputation
Data relating to the construction are Costs incurred Estimated costs to complete 2010 $1,650,000 1,350,000 2011 $1,375,000
Step by Step Solution
3.37 Rating (172 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style43 msonumberformat 000 000 00220022 msostylenameComma msostyleid3 style0 msonumberformatGeneral textaligngeneral vertical... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
68-B-A-F-S (2987).xlsx
300 KBs Excel File