Question: Dante Development Corporation is considering bidding on a contract for a new office building complex. Figure shows the decision tree prepared by one of Dantes
Dante Development Corporation is considering bidding on a contract for a new office building complex. Figure shows the decision tree prepared by one of Dante’s analysts. At node 1, the company must decide whether to bid on the contract. The cost of preparing the bid is $200,000. The upper branch from node 2 shows that the company has a 0.8 probability of winning the contract if it submits a bid. If the company wins the bid, it will have to pay $2,000,000 to become a partner in the project. Node 3 shows that the company will then consider doing a market research study to forecast demand for the office units prior to beginning construction. The cost of this study is $150,000. Node 4 is a chance node showing the possible outcomes of the market research study.
Nodes 5, 6, and 7 are similar in that they are the decision nodes for Dante to either build the office complex or sell the rights in the project to another developer. The decision to build the complex will result in an income of $5,000,000 if demand is high and $3,000,000 if demand is moderate. If Dante chooses to sell its rights in the project to another developer, income from the sale is estimated to be $3,500,000. The probabilities shown at nodes 4, 8, and 9 are based on the projected outcomes of the market research study.
a. Verify Dante’s profit projections shown at the ending branches of the decision tree by calculating the payoffs of $2,650,000 and $650,000 for first two outcomes.
b. What is the optimal decision strategy for Dante, and what is the expected profit for this project?
c. What would the cost of the market research study have to be before Dante would change its decision about the market research study?
d. Develop a risk profile for Dante.
DECISION TREE FOR THE DANTE DEVELOPMENTCORPORATION
.png)
Profit ($ 1000s ) High Demand 250 Build Complex Moderate Demand 650 Forecast High 0.6 0.15 Sell 1150 High Demand 250 Moderate Demand 6s0 1150 High Demand 2oo Market Research Build Complex Forecast Moderate 0.775 Win Contract Sell Build Complex Bid Moderate Demand 0.4 No Market Research Sell 1300 Lose Contract -200 Do Not Bid
Step by Step Solution
3.38 Rating (176 Votes )
There are 3 Steps involved in it
a Outcome 1 in 000s Bid 200 Contract 2000 Market Research 150 High Demand 5000 2650 Outcome 2 in 000... View full answer