Question: Day, Corp., is considering the use of activity-based costing. The following information is provided for the production of two product lines: Day plans to produce
Day, Corp., is considering the use of activity-based costing. The following information is provided for the production of two product lines:
.png)
Day plans to produce 400 units of Product A and 375 units of Product B.
Requirement
1. Compute the ABC indirect manufacturing cost per unit for eachproduct.
Activity Cost Cost Driver Number of setups Setup 106,000 Machine maintenance 55,000 Machine hours Total indiroct manufacturing costs 24 161,000 Product B Total Product A Direct labor hours 6,500 5,500 12,000 Number of setups 20 180 200 Number of machine hours 2,400 4,000 1,600 %24
Step by Step Solution
3.55 Rating (166 Votes )
There are 3 Steps involved in it
Req 1 Cost allocation rates Setup 106000 200 setups 530 per setup Machine maint... View full answer