Question: Decker & Co. makes electronic components. Chris Decker, the president, recently instructed Vice President Jim Bruegger to develop a total quality control program. If we
a. Costs incurred by Decker customer representatives traveling to customer sites to repair defective products, $13,500.
b. Lost profits from lost sales due to reputation for less-than-perfect products, $35,000.
c. Costs of inspecting components in one of Decker’s production processes, $22,500.
d. Salaries of engineers who are redesigning components to withstand electrical overloads, $90,000.
e. Costs of reworking defective components after discovery by company inspectors, $25,000.
f. Costs of electronic components returned by customers, $55,000.
Classify each item as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost. Then determine the total cost of quality by category.
Step by Step Solution
3.35 Rating (185 Votes )
There are 3 Steps involved in it
Prevention Cost Appraisal Cost I... View full answer