Question: Dickson contracted to build a house for Moran. When it was approximately 25 percent to 40 percent completed, Moran would not let Dickson work anymore

Dickson contracted to build a house for Moran. When it was approximately 25 percent to 40 percent completed, Moran would not let Dickson work anymore because he was not following the building plans and specifications and there were many defects. Moran hired another contractor to correct the defects and finish the building. Dickson sued Moran for breach of contract, claiming that he had substantially performed the contract up to the point where he had been discharged. Was Dickson correct? [Dickson v Moran, 344 So2d 102 (La App)]

Step by Step Solution

3.52 Rating (176 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

No There was no substantial performance ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

131-L-B-L-C (879).docx

120 KBs Word File

Students Have Also Explored These Related Business Law Questions!