During 2004, Abdulla Construction Company started a two-year construction project having a total contract price of $1,800,000.
Question:
During 2004, Abdulla Construction Company started a two-year construction project having a total contract price of $1,800,000. At December 31, 2004, the firm’s construction engineers estimated that the project was 35% completed. To date, 35% of the budgeted $1,250,000 in costs had been incurred. What amounts of
(a) Revenue,
(b) Expense, and
(c) Gross profit should be reported by this company at the end of 2004?