Question: During March 2011, Siebers Tool & Die Company worked on four jobs. A review of direct labor costs reveals the following summary data. Analysis reveals
During March 2011, Siebers Tool & Die Company worked on four jobs. A review of direct labor costs reveals the following summary data.
.png)
Analysis reveals that Job A257 was a repeat job. Job A258 was a rush order that required overtime work at premium rates of pay. Job A259 required a more experienced replacement worker on one shift. Work on Job A260 was done for one day by a new trainee when a regular worker was absent.
Instructions
Prepare a report for the plant supervisor on direct labor cost variances for March. The report should have columns for
(1) Job No.,
(2) Actual Hours,
(3) Standard Hours,
(4) Quantity Variance,
(5) Actual Rate,
(6) Standard Rate,
(7) Price Variance, and
(8)Explanation.
Actual Standard Total Job Number A257 Hours Costs $4,400 9,900 6,150 2,070 Hours Costs Variance $100 F 1,300 U 150 U 130 F 1,220 U 5 220 450 3 $4,500 8,600 6,000 A259 A260 115 Total variance
Step by Step Solution
3.45 Rating (177 Votes )
There are 3 Steps involved in it
SIEBERS TOOL DIE COMPANY Direct Labor Variance Report For the Month ... View full answer