During the last six weeks, the actual costs of materials were as follows: Week 1 $47,500 Week

Question:

During the last six weeks, the actual costs of materials were as follows:

Week 1 $47,500 Week 4 $50,000

Week 2 $52,500 Week 5 $60,000

Week 3 $60,000 Week 6 $65,000

The standard materials cost for each week was $50,000 with an allowable deviation of ± 5,000.