Question: During the most recent month at Coggan Corporation, queue time was 5.3 days, inspection time was 0.5 day, process time was 1.9 days, wait time
Required:a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent in non-value-added activities?
d. Compute the delivery cycle time.
Step by Step Solution
3.45 Rating (161 Votes )
There are 3 Steps involved in it
a Throughput time Process time Inspection time Move time Queue time 19 ... View full answer